산업안전보건법 시행령 제59조(기술지도계약 체결 대상 건설공사 및 체결 시기)
Enforcement Decree of the Occupational Safety and Health Act, Article 59 (Construction Work Subject to Technical Guidance Contracts, and When to Conclude Them)
① 법 제73조제1항에서 "대통령령으로 정하는 건설공사"란 공사금액 1억원 이상 120억원(「건설산업기본법 시행령」 별표 1의 종합공사를 시공하는 업종의 건설업종란 제1호의 토목공사업에 속하는 공사는 150억원) 미만인 공사와 「건축법」 제11조에 따른 건축허가의 대상이 되는 공사를 말한다. 다만, 다음 각 호의 어느 하나에 해당하는 공사는 제외한다. <개정 2022.8.16>
(1) The term "construction work prescribed by Presidential Decree" in Article 73 (1) of the Act means construction work with a construction amount of at least 100 million won but less than 12 billion won (15 billion won for work belonging to the civil engineering business under item 1 of the construction business column for businesses that carry out general construction work in attached Table 1 of the Enforcement Decree of the Framework Act on the Construction Industry), and construction work subject to building permission under Article 11 of the Building Act: Provided, That any of the following construction work is excluded:
1. 공사기간이 1개월 미만인 공사
1. Construction work with a construction period of less than one month;
2. 육지와 연결되지 않은 섬 지역(제주특별자치도는 제외한다)에서 이루어지는 공사
2. Construction work carried out on an island not connected to the mainland (excluding Jeju Special Self-Governing Province);
3. 사업주가 별표 4에 따른 안전관리자의 자격을 가진 사람을 선임(같은 광역지방자치단체의 구역 내에서 같은 사업주가 시공하는 셋 이하의 공사에 대하여 공동으로 안전관리자의 자격을 가진 사람 1명을 선임한 경우를 포함한다)하여 제18조제1항 각 호에 따른 안전관리자의 업무만을 전담하도록 하는 공사
3. Construction work for which the business owner has appointed a person with the qualifications of a safety officer under attached Table 4 (including where one person with the qualifications of a safety officer has been jointly appointed for not more than three construction works carried out by the same business owner within the area of the same Metropolitan local government) and has that person devote himself or herself exclusively to the duties of a safety officer under the subparagraphs of Article 18 (1);
4. 법 제42조제1항에 따라 유해위험방지계획서를 제출해야 하는 공사
4. Construction work for which a hazard and risk prevention plan must be submitted under Article 42 (1) of the Act.
② 제1항에 따른 건설공사의 건설공사발주자 또는 건설공사도급인(건설공사도급인은 건설공사발주자로부터 건설공사를 최초로 도급받은 수급인은 제외한다)은 법 제73조제1항의 건설 산업재해 예방을 위한 지도계약(이하 "기술지도계약"이라 한다)을 해당 건설공사 착공일의 전날까지 체결해야 한다. <신설 2022.8.16>
(2) The construction project owner or construction principal contractor (excluding, as the construction principal contractor, the contractor who first received the contract for the construction work from the construction project owner) of construction work under paragraph (1) shall conclude the guidance contract for preventing construction industrial accidents under Article 73 (1) of the Act (hereinafter referred to as a "technical guidance contract") by the day before the start date of the construction work.
영어는 이 사이트가 원문에서 옮긴 비공식 번역으로, 영어 공부를 돕기 위한 것입니다. 법적 효력은 한국어 원문에만 있습니다. 낱말 위 한글은 소리 나는 대로 적은 발음이며 굵은 글자가 강세입니다.
시행 2026.8.1 · 대통령령 · 고용노동부 소관